Installation testing and maintenance of electrical installations Paper - 3
विद्युत संस्थापनाओं की संस्थापना , परीक्षण तथा उनका अनुरक्षण - प्रश्न पत्र 3
CHAPTER- 1
1. Sections of Electricity Act 2003 / विद्युत अधिनियम 2003 की धाराए
CHAPTER 1. Section of Electricity Act 2003
2,7,8,9,12,13,42,43,52,53,54,55,56,67,68,126,127,128,135,136,138,153
154,161,162,163,164,170,171,176,177,180,181 I
PART VIII
WORKS
Works of licensees
Section 67. (Provisions as to opening up of streets,railways, etc)
Section 68. (Provisions relating to Overhead lines)
Section 67. (Provisions as to opening up of streets, railways, etc)
Section 67. (Provisions as to opening up of streets, railways, etc): — (1) A
licensee may, from time to time but subject always to the terms and conditions of
his licence, within his area of supply or transmission or when permitted by the
terms of his licence to lay down or place electric supply lines without the area of
supply, without that area carry out works such as –
(a) to open and break up the soil and pavement of any street,
railway or tramway;
(b) to open and break up any sewer, drain or tunnel in or under
any street, railway or tramway;
(c) to alter the position of any line or works or pipes, other than
a main sewer pipe;
(d) to lay down and place electric lines, electrical plant and
other works;
(e) to repair, alter or remove the same;
(f) to do all other acts necessary for transmission or supply of
electricity.
(2) The Appropriate Government may, by rules made by it in this behalf,
specify, –
(a) the cases and circumstances in which the consent in writing
of the Appropriate Government, local authority, owner or
occupier, as the case may be, shall be required for carrying
out works;
(b) the authority which may grant permission in the
circumstances where the owner or occupier objects to the
carrying out of works;
(c) the nature and period of notice to be given by the licensee
before carrying out works;
(d) the procedure and manner of consideration of objections and
suggestion received in accordance with the notice referred to
in clause (c);
(e) the determination and payment of compensation or rent to
the persons affected by works under this section;
(f) the repairs and works to be carried out when emergency
exists;
(g) the right of the owner or occupier to carry out certain works
under this section and the payment of expenses therefor;
(h) the procedure for carrying out other works near sewers,
pipes or other electric lines or works;
(i) the procedure for alteration of the position of pipes, electric
lines, electrical plant, telegraph lines, sewer lines, tunnels,
drains, etc.;
(j) the procedure for fencing, guarding, lighting and other
safety measures relating to works on streets, railways,
tramways, sewers, drains or tunnels and immediate
reinstatement thereof;
(k) the avoidance of public nuisance, environmental damage
and unnecessary damage to the public and private property
by such works;
(1) the procedure for undertaking works which are not
repairable by the Appropriate Government, licensee or local
authority;
(m) the manner of deposit of amount required for restoration of
any railways, tramways, waterways, etc.;
(n) the manner of restoration of property affected by such works
and maintenance thereof;
(o) the procedure for deposit of compensation payable by the
licensee and furnishing of security; and
(p) such other matters as are incidental or consequential to the
construction and maintenance of works under this section.
(3) A licensee shall, in exercise of any of the powers conferred by or under
this section and the rules made thereunder, cause as little damage, detriment
and inconvenience as may be, and shall make full compensation for any damage,
detriment or inconvenience caused by him or by any one employed by him.
(4) Where any difference or dispute [including amount of compensation
under sub-section (3)] arises under this section, the matter shall be determined by
the Appropriate Commission.
(5) The Appropriate Commission, while determining any difference or dispute
arising under this section in addition to any compensation under sub-section (3),
may impose a penalty not exceeding the amount of compensation payable under
that sub-section.
PART I
PRELIMINARY
Section 1. (Short title, extent and commencement) — (1)This Act may be called the Electricity Act, 2003.
(2) It extends to the whole of India except the State of Jammu and Kashmir.
(3) It shall come into force on such date as the Central Government may, by notification, appoint:
Section 2. (Definitions):- — In this Act, unless the context otherwise requires
PART III
GENERATION OF ELECTRICITY
Section 7. (Generating company and requirement for setting up of generating station)
Section 8. (Hydro-electric generation)
Section 9. (Captive generation)
PART IV
LICENSING
Section 12. (Authorised persons to transmit, supply, etc., electricity)
Section 13. (Power to exempt)
PART VI
DISTRIBUTION OF ELELCTRICITY
Provisions with respect to distribution licensee
Section 42. (Duties of distribution licensee and open access)
Section 43. Section 43. (Duty to supply on request)
Section 52. (Provisions with respect to electricity traders)
Section 53. (Provisions relating to safety and electricity supply)
Section 54. (Control of transmission and use of electricity)
Section 55. (Use, etc., of meters)
Section 56. (Disconnection of supply in default of payment)
PART VIII
WORKS
Works of licensees
Section 67. (Provisions as to opening up of streets,railways, etc)
Section 68. (Provisions relating to Overhead lines)
PART XII
INVESTIGATION AND ENFORCEMENT
Section 126: (Assessment)
Section 127. (Appeal to Appellate Authority)
Section 128. (Investigation of certain matters)
PART XIV
OFFENCES AND PENALTIES
Section 135. (Theft of Electricity)
Section 136. (Theft of electric lines and materials)
Section 138. (Interference with meters or works of licensee)
PART XV
SPECAIL COURTS
Section 153. (Constitution of Special Courts)
Section 154. (Procedure and power of Special Court)
Section 161. (Notice of accidents and injuries)
Section 162. (Appointment of Chief Electrical Inspector and Electrical Inspector)
Section 163. (Power for licensee to enter premises and to remove fittings or other apparatus of licensee)
Section 164. (Exercise of powers of Telegraph Authority in certain cases)
PART XVIII
MISCELLANEOUS
Section 170. (Recovery of penalty payable under this Act)
Section 171. (Services of notices, orders or documents)
Section 176. (Power of Central Government to make rules)
Section 177. (Powers of Authority to make regulations)
Section 180. (Powers of State Governments to make rules)
Section 181. (Powers of State Commissions to make regulations)
MP ELECTRICAL SUPERVISOR LICENCE EXAM
केन्द्रीय विद्युत प्राधिकरण (सुरक्षा एवं विद्युत आपूर्ति संबंधी उपाय) विनियम 2010 के विनियम 29 में प्रावधान है कि स्थापना का स्वामी, विद्युत ठेकेदार, परमिटधारी व्यक्ति से कार्य करायेगा। परमिटधारी व्यक्ति से तात्पर्य यह है कि फिटिंग करने वाला व्यक्ति जैसे घरेलू वायरिंग, औद्योगिक फिटिंग, शिरोपरि लाइनें एवं भूमिगत केबल की स्थापना का कार्य।
इलेक्ट्रिशियन के द्वारा विद्युत फिटिंग का कार्य संपादित किया जायेगा, जिन्होंने कार्य करते हुए दो वर्ष का अनुभव लिया है। इसके बाद वह वायरमेन की परीक्षा दे सकते हैं।
विद्युत व्यवस्था में डिजाइन, योजना एवं कार्य कराने वाला व्यक्ति, एक अन्य व्यक्ति है, जो परमिटधारी इलेक्ट्रिशियन व्यक्तियों के माध्यम से कार्य करा सकता है और ऐसे कार्य कराने वाले व्यक्ति तकनीकी रूप से दक्ष होकर विद्युत स्थापना का पर्यवेक्षण करते हैं। ऐसे पर्यवेक्षण करने वाले व्यक्ति को यह आवश्यक है कि विनियम 29 के अंतर्गत सुपरवाइज़र परमिट प्राप्त करें। सुपरवाइज़र परमिट प्राप्त करने के लिए यह आवश्यक है कि वह तकनीकी योग्यता के साथ-साथ कम से कम 2 वर्ष का व्यावहारिक अनुभव रखता हो ताकि वह भिज्ञ हो सके कि व्यक्ति वास्तविक विद्युत का कार्य कराने के लिए दक्ष हो गया है। पर्यवेक्षक परीक्षा देकर उत्तीर्ण करने के बाद वह पर्यवेक्षक परमिटधारी व्यक्ति हो जाता है।



APPLY ONLINE
OLD PAPERS
Eligbility
Rules and Regulation for Applying Under Supervisory Exam
1- Applying under mining
A- If Candidate have: 10+2 with (PCM)+ITI (Electrician trade)+ 5 years
Experience, candidate will give paper 1st 4th & mining oral/practical.
B- if Candidate have: 10+2 with (PCM)+ tar mistry (wiremen) permit passed in 2
subject (2 out of 4) +5 years’ experience. Candidate will give paper 1st 4th & mining
oral/practical.
C- If Candidate have: degree/diploma in engineering (other than Electrical)+ 2
years experience. Candidate will be eligible to give paper 1st,4th & mining
oral/practical.
D- If candidate have: degree/diploma in (Electrical)+ 2 years experience.
Candidate will be eligible to give paper 4th& mining oral/practical only.
2- Applying under non mining
A- If candidate have: 10+2 with (PCM)+ITI (Electrician trade)+5 years experience,
candidate will be eligible to give paper 1st, 2nd, 3rd and non mining oral/practical.
B- If candidate have: 10+2 with (PCM)+ tar mistry (wiremen) permit passed in 2
subject (2 out of 4)+5 years experience, candidate will give paper 1st, 2nd, 3rd & non
mining oral/practical.
C- If candidate have: degree/diploma/polytechnic in engineering (other than
Electrical)+ 2 years experience, candidate will give paper 1st ,2nd, 3rd & non mining
oral/practical.
D- If candidate have: degree/diploma in (Electrical)+ 2 years experience,
candidate will be eligible to give paper 3rd only.
3- Applying under both for mining/non mining, rules will be taken
Commonly as mention above.
4. Mandatory Terms and Conditions
1. It is mandatory that the departmental fee for mining and non mining is Rs.40/-
for each examination and in case of Both department fees will be Rs 80 and to be
paid by cyber treasury.
2. Work experience from outside the State of Madhya Pradesh is not acceptable
And not allowed.
3. The experience of the Contractor will only be valid when candidate has been
Registered as a trainee in the M.P. Licensing Board (Electrical safety
Department).
4. Only High Tension Consumer work experience will be acceptable.
5. It is mandatory that the applicant is being lived in Madhya Pradesh State for
at least 3 years.
6. Experience Certificate should be issued on Institution’s Letter-head including
The competency of the Institution, Name and the designation of the issuing
Officer with their email id & mobile number.
7. 2 years work experience is mandatory after the completion of Diploma
/Degree in Engineering.
8. 5 years work experience is mandatory after the completion of 12th PCM+ITI
(Electrician trade)
9. 5 years work experience is mandatory after the completion of 12th
PCM+ wireman permit any 2 subject. (Domestic, industrial, overhead,
Underground)
10. Work experience is not acceptable before last 5 year.
11. If the candidate is applying for mining subject then the experience is
Mandatory for mining work. (ex:-coal mines)